Baoshan Road, demolition of old buildings accident to lie down

Category: Ningbo News
Published: Monday, 16 July 2012 10:51

Source 2012-7-16 8:39:19 Ningbo Evening News

The scene
  Reporter Zhang Xerox intern Lijia Yang Minimizers text / photo
  Yesterday morning, a Cangsong Road and Baoshan Road junction is being dismantled buildings, suddenly and unexpectedly tilted as a whole lie down. No safety net to protect the buildings, masonry and fixtures falling, smashing is a car came by, causing body damage.
  The demolitions gravel smashing damage the car crossing the road
  9 o'clock yesterday morning, the ongoing demolition of a building located in the pines Road, Haishu District, Baoshan Road junction. The public Zhuang Ms. drive from Baoshan Road after just emerged from the pine trees with road Guaixiang. At this point, with the rumbling series of loud noise, some brick and fixtures fell from the sky to drop in on the car of Ms. Zhuang, resulting in Ms. Chong's car shell damage.
  After the incident, Ms. Chong to the newspaper immediately 87777777 News hotline phone call to each other barbaric construction, injuring her car, hoping to seek media support. Since then, passing by some members of the public are also photographed and sent to microblogging online.
  According to an eyewitness, the incident occurred, it was still under the rain, fall, building rubble and its attachments in addition to hit Ms. Chong's car, but also scattered into the middle of the road of Baoshan Road.
  Nearby residents surveyed rejoice to say that thanks to the car can block, I hit the pedestrian here, I am afraid will Shangdebuqing.
  According to reporter understanding, here are tearing down the building of the original Shun Wang-based restaurant, demolition is to make way for Wing Tat Road. Nearby residents told reporters that the demolition work has been carried out for several days.
  Close to the road demolitions, but no safety net
  Yesterday, reporters rushed to the scene, Ms. Chong's car drove away, construction has been suspended, not construction workers, only the demolitions broken disassemble stop at the scene.
  Look at the demolished building, the overall west north side of the side part of the wall at the risk of collapse. From passers-by were surprised to inquire: how the house is split into such a collapse, no injuries to people?
  Found at the scene reporters after the incident, the construction site still did not pull the safety net, only at the site of the Zhuang Ms. car smashed more than a few bunting rope surround. Baoshan Road, next to this building dangerous building is still a steady stream of vehicles and pedestrians.
  According to nearby shops, the house fell to the ground, the sound was very loud, Prior, and there is no sign of the collapse of road vehicles and pedestrians do not have to prepare, in this loud noise surprised.
  Residents of the one at the scene questioned this, Chai Fangzi close to the road, why do not you set up a safety net?
  Mayor microblogging called for the strengthening of management prevent accidental
  Yesterday morning, the users of the microblogging online have reproduced, 11:11, Haishu District, Mayor Wu Shengwu microblogging @ Boming long, deputy head of the relevant departments and Haishu District Work Safety Supervision Bureau Haishu District Urban Management Bureau, the request to the deliberations of this things, strengthen management, to prevent accidents.
  Yesterday afternoon, the reporter again call Ms. Chong is trying to reason and deal with progress of the inquiry event, however, other party is unwilling to bring the process and outcome of the matter, saying only that the matter has been resolved.
  Yesterday afternoon, Haishu District Urban Management Bureau of Baiyun squadron staff rushed to the scene learned that Ms. Chong is with the construction side to reach a compensation agreement, and received compensation payments. As for the removal process, whether the violations, not in the inquiry and the scope of management of urban management. Urban management and staff said that the 17 o'clock yesterday, the matter found that the field of road slag has been cleared, does not affect vehicle.
  Related Links
  Ningbo City housing demolition construction safety regulations. "
  Article 11 The contracting business in accordance with the provisions of the various demolition methods, delineation of hazardous areas, do a good job alert and warning signs, and reliable security measures. Removal of the project site must be set to the fence. In the urban areas the main sections of the roads on both sides of the fence height of not less than 2.5 meters, the fence should be clean and tidy, no damage shall be without prejudice to the city appearance. In urban areas on both sides of the main roads and residential areas around the demolition, must be fully enclosed in the form of steel scaffolding and dense mesh safety net, as necessary, erection of protective isolation shed.
  Demolition engineering work 16 should generally be top-down order, shall not be interchange demolition work.
  Article 19 in height demolition, vertical transportation equipment should be set or exile tank, removal of material prohibited thrown down; demolition under a variety of materials should be cleared up, and were stacked in the designated place.